ESF
(activity 1.1.1.2.) project "Forming of scientific
group for unified satellite laser ranging device design"
Stage 2 (April - June
2014)
During
stage 2 detailed design of mechanical assembly was finished. After that, specifications
of mechanical components were produced. As a result, now we have set of work
drawings and specifications, and manufacturing of components and fitting them
together can begin.
Software
design specifications are completed, coding of control software, has started.
First, positioning and predictions modules will be implemented.
Long
expected purchase tenders are announced, with delivery deadline in November
2014 - January 2015. If all goes well and no claims are rised, the result
timing can still be according to our schedule, if only just.
Presentations
about project have been delivered in the EUREF symposia in Vilnius and in ICCST
conference.
|